Updated March 14, 2013
2013 PRIMARY CONSTRUCTION
EXPANSION/ RECONSTRUCTION PROJECTS
Northland Drive – North of Indian
Lakes Road to South Street
Reconstruct and widen to 3-lane
all-season section. Includes
concrete curb and gutter, storm sewer, ditches and HMA pavement. Through traffic will be detoured. Work will be phased with work north of 16 Mile Road first and south of 16 Mile Road last.
Planned Start Date: June 10, 2013
Kraft
Avenue – 60th Street to 52nd Street
Reconstruct and widen south half to 3-lane all-season section and crush and shape and resurface the north half. Includes concrete curb and gutter, storm sewer, sanitary sewer and watermain extension (Cascade Township), and HMA pavement. Through traffic will be detoured.
Start Date: March 18, 2013
Contractor: Georgetown Construction
Completion Date: July 1, 2013
14 Mile Road – Edgerton
Avenue to US-131 Ramps
Widen to provide a center left-turn
lane from Edgerton Avenue to southbound US-131 ramps. Two-way traffic will be
maintained.
68th Street @ Morse Lake Avenue
Reconstruct and regrade 68th Street east and west of Morse Lake Avenue to improve sight distance, including
earthwork, drainage and HMA pavement. Through traffic will be detoured.
Planned Start Date: June 10, 2013
Knapp
Street & Grand River Drive
Reconstruct and regrade Knapp Street
west of Grand River Drive to improve sight distance, construct northbound to
eastbound right-turn lane on Grand River Drive. Modify and upgrade existing traffic signal. Traffic will be maintained with lane restrictions.
White Creek Avenue north
of 17 Mile Road
Reconstruct
and widen to provide a southbound right-turn lane at 17 Mile Road and center
left-turn lane north through existing commercial drive access. Through traffic will be detoured.
Planned Start Date: April 15, 2013
Contractor: Dean’s Landscaping & Excavating
Completion Date: June 30, 2013
Ada Drive & Spaulding Avenue
Modify
and upgrade existing traffic signal with box span configuration, LED signal
heads and camera detection. Modify
northwest curb radius and reconstruct existing sidewalk ramps.
RESURFACING PROJECTS
Cascade Road – Timpson Avenue to
Segwun Avenue
Cold mill existing
asphalt surface and crack & seat underlying concrete pavement. Resurface with HMA pavement. Through traffic will be detoured. Project will be phased with work west and east
of Alden Nash Avenue.
68th Street – Burlingame
Avenue to Clyde Park Avenue
Mill existing asphalt
surface. Resurface with HMA pavement. Through traffic will be detoured.
Planned Start Date: May 1, 2013
Contractor: Michigan Paving &
Materials
Completion Date: June 30, 2013
76th Street – Burlingame Avenue to
Sierrafield Drive
Crush and shape existing asphalt
surface. Resurface with HMA
pavement. Through traffic will be
detoured.
84th Street – Division
Avenue to Kalamazoo Avenue
Cold mill and crush
& shape existing asphalt surface. Resurface with
HMA pavement. Through traffic will be
detoured. Project will
be phased with work west and east of Eastern Avenue.
Planned Start Date: May 1, 2013
Contractor: Michigan Paving and Materials
Completion Date: June 30, 2013
BRIDGE PROJECT
Ada Bridge #5 – Knapp Street over the
Grand River
Pin
and hanger replacement, steel repair and seal concrete deck. Two-way traffic will be
maintained with a temporary traffic signal. The project will be coordinated with the
Knapp Street and Grand River Drive intersection project.
NON-MOTORIZED PROJECT
Musketawa Trail / White Pine Trail
Connector (Phase 2)
Construct
a 10-foot wide HMA trail from 3 Mile Road at Alpine Avenue to the White Pine
Trail at North Park Street.
| Kent County Road Commission | 1500 Scribner Ave. NW | Grand Rapids, Michigan 49504 | (616) 242-6900 |