10 Mile Road
Location: M37 and Alpine Avenue
Project Type: Pavement Reconstruction
Detour: Yes
Scheduled Start: September 6, 2016
Projected Completion: September 30, 2016
Work Completed by: Kamminga & Roodvoets
About Project: The existing asphalt surface will be crushed and regraded with a left turn lane added. The surface will then be covered with Hot Mix Asphalt (HMA). Restoration includes guardrail and pavement markings. The section of 10 Mile Road will be closed to through traffic for the duration of the project, with the posted detour, below.
Packer Drive
Location: Van Dam Drive to Rogue River Road
Project Type: Permit Work – Sewer Installation
Detour: Yes
Scheduled Start: September 6, 2016
Projected Completion: September 27, 2016
Work Completed by: Kamminga & Roodvoets
About Project: The permit work conducted on behalf of North Kent Sewer/Plainfield Township will consist of sanitary sewer siphon replacement under Packer Drive adjacent to the Rogue River. In late August, an existing gas main that conflicted with the sanitary sewer siphon replacement was relocated. The detour, below, will be posted for the duration of the project.