10 Mile Road (COMPLETE)

Schedule Date: May 7 - September 18, 2018

Location Detail: Alpine Avenue to Pine Island Drive

Reconstruct to 2-lane all season road standard. Work includes tree removal, earthwork, valley gutter, ditches, storm sewer, culvert replacement, HMA Pavement, pavement markings and restoration.This project will include widening and curb improvements at Vinton, Division, and Krupp avenues.

Information

Phase 1 - COMPLETE (Restoration underway)
Limits: Alpine Avenue to just west of Division Avenue
Schedule: May 7 – July 16
Traffic: Closed to through traffic
Work Update: Base paving is projected to begin late next week with top course paving to follow. Phase 1 restoration and driveway construction work will begin on June 13th and last approximately two weeks.

Phase 2 - COMPLETE (Restoration underway)
Limits: Intersection of 10 Mile Road and Division Avenue to 1000 feet east on 10 Mile Road
Schedule: June 13 – PJuly 16
Traffic: Intersection closed to through traffic

Phase 3 - Currently Underway - September 18, 2018 (Complete)
East of Division Avenue to west of Pine Island Drive
Work includes tree removal, earthwork, valley gutter, ditches, storm sewer, culvert replacement, HMA Pavement, pavement markings and restoration
Closed to through traffic