100th Street Bridge over Thornapple River

Schedule Date: June 11 - August 23, 2019

Location Detail: East of River Short Drive

The Kent County Road Commission has contracted C.A. Hull Co., Inc for the following:
1. Repair Bridge Substructure
2. Replace Bridge Expansion Joints
3. Place stone riprap around bridge piers

During repair of the bridge substructure, a temporary signal will be installed on the bridge and alternating one-lane traffic will be allowed to pass on the bridge. The temporary signal will be in place through approximately July 4th.

 After the substructure repair is complete, the expansion joints and stone placement will require full bridge closure via a posted detour (TBD). This work will require approximately 5 weeks to complete. 

Go Back