13 Mile Road (COMPLETE)

Schedule Date: July 23 - November 14, 2018 (open to traffic) May 2019 (final restoration)

Location Detail: Kenowa Avenue to Peach Ridge Avenue

Reconstruct to 2-lane all season road standard. Work includes tree removal, earthwork, valley gutter, ditches, drainage, culvert extensions, HMA pavement, pavement markings and restoration. This project will be completed in three phases and closed to through traffic with a posted detour. Local traffic will be maintained for property owners and emergency vehicles.  

CURRENT WORK: Phase 3 - 13 Mile Road and Fruit Ridge Avenue Intersection (9/19 - 11/2/18)

Information

This project will be constructed in phases to minimize the impact on local property  owners.        

  • Phase 1 will consist of the closure and construction of 13 Mile Road from Kenowa Ave. to west of Fruit Ridge Ave through the base course paving and the restoration.
  • Phase 2 will consist of the closure and construction of 13 Mile Road from east of Fruit Ridge Ave  to Peach Ridge Ave through the base course paving and the restoration.
  • Phase 3 will consist of the construction of Fruit Ridge Ave intersection.

NOTICE RE 13 MILE RD PROJECT