Schedule Date: 2019

Location Detail: East Rivershores Drive

The following is a paving project scheduled for the 2019 construction season cost-shared between the township and the Kent County Road Commission.

Information

Road Improvement Project: Full Mill & Fill

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

Contractor: Superior

Road receiving improvement:

  • East Rivershores Drive (100th St to 100th St)