Major Road Projects

Category Navigation

10 Mile Road (at Belmont Avenue)

Schedule Date: May 9 - May 18, 2018

Location Detail: just east and west of Belmont Avenue

The existing traffic signal at 10 Mile Road and Belmont Avenue will be removed and a concrete median divider will be constructed on 10 Mile Road to deter left-hand turns onto Belmont Avenue. Those seeking to make a left-hand turn from 10 Mile Road should now use the newly completed Belmont Bypass.

10 Mile Road (COMPLETE)

Schedule Date: May 7 - September 18, 2018

Location Detail: Alpine Avenue to Pine Island Drive

Reconstruct to 2-lane all season road standard. Work includes tree removal, earthwork, valley gutter, ditches, storm sewer, culvert replacement, HMA Pavement, pavement markings and restoration.This project will include widening and curb improvements at Vinton, Division, and Krupp avenues.

100th Street Bridge (MDOT - Emergency Repair)

Schedule Date: April 23 - May 23, 2018

Location Detail: Over US-131

100th Street Bridge is under the jurisdiction of the Michigan Department of Transportation (MDOT), not KCRC.

The Michigan Department of Transportation (MDOT) will begin emergency construction on the 100th Street Bridge over US-131 in Byron Township tomorrow, Monday, April 23 at 7PM - the bridge will remain closed to traffic through June 1.

The detour routes include:

EB 100th Street Detour: SB US-131 to 142nd Street to NB US-131 to EB 100thStreet

WB 100th Street Detour: NB US-131 to 84th Street to SB US-131 to WB 100th Street

The bridge was damaged when two semi-trucks with over-height shipping containers struck the overpass - this emergency repair project will restore two-way traffic.

MDOT has tentatively scheduled to replace and upgrade the bridge in 2020.

13 Mile Road (COMPLETE)

Schedule Date: July 23 - November 14, 2018 (open to traffic) May 2019 (final restoration)

Location Detail: Kenowa Avenue to Peach Ridge Avenue

Reconstruct to 2-lane all season road standard. Work includes tree removal, earthwork, valley gutter, ditches, drainage, culvert extensions, HMA pavement, pavement markings and restoration. This project will be completed in three phases and closed to through traffic with a posted detour. Local traffic will be maintained for property owners and emergency vehicles.  

CURRENT WORK: Phase 3 - 13 Mile Road and Fruit Ridge Avenue Intersection (9/19 - 11/2/18)

13 Mile Road (Culvert)

Schedule Date: August 28 - October 31, 2018

Location Detail: Fruit Ridge Avenue to Peach Ridge Avenue

13 Mile Rd from Fruit Ridge Ave to Peach Ridge Ave has daytime lane closures for culvert work.

14 Mile Road

Schedule Date: April 30 - May 11, 2018

Location Detail: Lymburner Avenue to Pine Island Drive

Project: ​Crush & shape, repave

16 Mile Road

Schedule Date: Completion: October 2018

Location Detail: Keller Avenue to Harvard Avenue

The proposed improvement of 1.01 miles of 16 Mile Road from Keller Avenue to Harvard Avenue in Section 6 of Oakfield Township and Section 31 of Spencer Township includes necessary tree removal, grading, drainage, subbase, aggregate base and construction to provide for a 30-foot width roadway with HMA surfacing.

18 Mile Road (COMPLETE)

Schedule Date: August 6 - August 25, 2018

Location Detail: Wabasis Avenue to Meddler Avenue

Project will include cold milling then a full Crush & Shape, repaved with 3.5" of Hot Mix Asphalt (HMA).

30th Street (COMPLETE)

Schedule Date: August 16 - September 7, 2018

Location Detail: Wycliffe Drive to Buttrick Avenue

This is a crush & shape project: a structural pavement treatment that grinds, or crushes, the existing asphalt and 1-2” of underlying gravel. The material is then regraded, compacted and covered with three and a half inches of Hot Mix Asphalt (HMA).

4 Mile Road (COMPLETE)

Schedule Date: October 8 - November 1, 2018

Location Detail: Egypt Valley to .25 miles west

Road closed to through traffic for road construction.

48th Street

Schedule Date: April 12 - May 25, 2018

Location Detail: East of Thornapple River Drive

The north side of the road approaching Thornapple River Drive is being widened to provide westbound to northbound right-turn lane. Road is being completed with shoulder closures.

60th Street (Utility Work) (COMPLETED)

Schedule Date: April 9 - July 31, 2018

Location Detail: Burlingame Avenue and Clyde Park Avenue

Work includes extending sanitary sewer and watermain within 60th Street right-of-way from 100 feet east of Burlingame Avenue to 700 feet east of Burlingame Avenue. Disturbed portion of 60th Street will be reconstructed to all-season.

60th Street (west of Broadmoor Avenue) -(COMPLETE)

Schedule Date: September 26 - October 31, 2018

Location Detail: West of Broadmoor Avenue

Project consists of adding right turn lane on northbound Patterson Avenue south of 60th Street and an additional right turn lane on eastbound 60th Street west of Broadmoor Avenue.

Traffic: Right lane closure at 60th Street west of Broadmoor Avenue; traffic maintained
Contractor: Miller Brothers Construction 

64th Street (Complete)

Schedule Date: August 13 - October 12, 2018

Location Detail: Burlingame Avenue and Woodspointe Drive

Closed for sanitary sewer work and a crush, shape and repave.

68th Street (West of Broadmoor Avenue) (COMPLETE)

Schedule Date: September 26 - November 8, 2018

Location Detail: West of Broadmoor Avenue

Project consists of adding an additional right turn lane on eastbound 68th Street west of Broadmoor Avenue.
Traffic: Lane closures; two-way traffic maintained
Contractor: Miller Brothers Construction

68th Street at Patterson Avenue (COMPLETE)

Schedule Date: September 17 - November 9, 2018

Location Detail: East and West of Patterson Avenue

Widening 68th Street west and east of Patterson Avenue for additional (dual) eastbound to northbound left-turn lanes. Work will be completed using lane closures.

68th Street Bridge over the Thornapple River (Completed)

Schedule Date: June 12 – July 25, 2018

The project includes bridge deck latex concrete resurfacing, hydro demolition, bridge joint replacement and approach work.
Traffic: bridge closure; detour posted

7 Mile Road (COMPLETE)

Schedule Date: October 22 - November 2, 2018

Location Detail: Bristol to M-37

Crosstile Replacement - Road Closed; Detour posted

72nd Street (COMPLETE)

Schedule Date: August 2018

Location Detail: Ivanrest to Byron Center Avenue

Ivanrest to Byron Center (Crush & Shape)

  • Crush & Shape is a structural pavement treatment that grinds, or crushes, the existing asphalt and 1-2” of underlying gravel. The material is then regraded, compacted and covered with multiple layers of paver-placed hot asphalt.

72nd Street (COMPLETE)

Schedule Date: October 29 - November 9, 2018

Location Detail: Byron Center Avenue to Burlingame Avenue

During this resurfacing project, the existing asphalt surface layer will be milled out and replaced with two courses of Hot Mix Asphalt (HMA), a total of 3.5 inches thick. Traffic will be closed to through traffic with a detour posted. (Traffic detoured to 68th Street)

82nd Street (COMPLETE)

Schedule Date: July 31 - August 31, 2018

Location Detail: Kenowa Avenue and Wilson Avenue

Project: Crush & Shape

Crush & Shape is a structural pavement treatment that grinds, or crushes, the existing asphalt and 1-2” of underlying gravel. The material is then regraded, compacted and covered with multiple layers of paver-placed hot asphalt.

Ada Drive (COMPLETE)

Schedule Date: October 26 - November 8, 2018

Location Detail: Bronson Street to Headley Street

Concrete curb & gutter modifications on Ada Drive between Bronson and Headley to delineate parking areas, concrete cross-walks and brick paver parkways. Ada Drive westbound detoured to Fulton Street west to Spaulding and south to Ada Drive. Ada Drive eastbound traffic will be maintained.

Alpenhorn Drive

Schedule Date: July 2 - October 26, 2018

Location Detail: .2 miles south of Lamoreaux Drive

Replacement of CMP culvert with a precast concrete box culvert. Bridge will be closed to all traffic - including pedastrian traffic - for the duration of the project.

Argo Street

Schedule Date: May 1 - May 10, 2018

Location Detail: Between Ada Drive and Cascade Road

Mill and fill project. Construction will be completed with road closed to through traffic.

Bell Lake Drive

Schedule Date: May 17 - May 22, 2018

Location Detail: McCabe to the End

The paving project will include one course of 2” hot mix asphalt overlay.

Bella Vista Drive

Schedule Date: June 4 - June 15, 2018

Location Detail: Bella Vista (Belding Rd to Myers Lake)

Bella Vista: Mill & Fill (Resurfacing)
Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.
 

Belmont Avenue

Schedule Date: May 23 - June 8, 2018

Location Detail: Pine Hill Drive to South of Belmont Bypass

​Project: Crush & Shape and Resurfacing

Crush & Shape is a structural pavement treatment that grinds, or crushes, the existing asphalt and 1-2” of underlying gravel. The material is then regraded, compacted and covered with multiple layers of paver-placed hot asphalt. ("Road Closed" sign posted at 10 Mile Ave and Belmont Ave)

Belmont Avenue

Schedule Date: May 9 - May 23, 2018

Location Detail: Belmont Bypass to 10 Mile Road

​The project consists of a mill and fill. The road will be closed to through traffic for the project’s duration.

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

Belmont Bypass

Schedule Date: Completed May 4, 2018

Location Detail: South of 10 Mile Road

A new road is being constructed from 10 Mile Road and Thrifty Drive, south and west, to Belmont Avenue. Belmont Avenue is being widened from Graphic Drive south approximately 500 feet.Construction of new all season road will divert 10 Mile & Belmont Avenue left turns to the signalized intersection at the Meijer Entrance on 10 Mile Road. This project will provide for a three-lane roadway, with one lane in each direction and a center turn lane.

Bostwick Lake View Drive, Summerwind Avenue and Summer Lane Avenue

Schedule Date: June 6-June 11 2018

Location Detail: Bostwick Lake View Dr (9 Mile Road to End); Summerlane Avenue (5 Mile to Summerwind); Summerwind Avenue (5 Mile to end)

Project will include an Ultra Thin Overlay with a chipseal interlayer. 

Bristol Avenue

Schedule Date: May 2 - May 18, 2018

Location Detail: 4 Mile Road to Alpine Church Road

Project: Crosstile replacement and Crush & shape

Brower Lake Dr, Brower Ave and Oakview Ave

Schedule Date: May 22 - June 8, 2018

Project: Mill & Fill

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

Campau Lake Streets (Caledonia) (COMPLETE)

Schedule Date: September 25 - October 5, 2018

Project consists of mill & fill; completed with lane closures.

Cannon Twp: Arroyo Vista Dr, Bella Vista, Knollcrest, Silverwick and Cannon Meadows

Schedule Date: May 16 - June 1, 2018

Location Detail: Arroyo Vista (Blakely to 9 Mile) Bella Vista (Belding Rd to Myers Lake) Knollcrest (Myers Lake to End) Silverwick (young to end) Cannon Meadows (Pettis to End)

​These streets will receive a full mill & fill.

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

Cascade Road

Schedule Date: Week of May 29 – June 22, 2018

Location Detail: Fulton Street to East Beltline Avenue

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer with a milling machine and the replacement of the milled location with new asphalt

Cascade Springs Subdivision (COMPLETE)

Schedule Date: July 17 - September 14, 2018

Location Detail: Off of Cascade Road

There will be road closures/lane closures for a mill and repave.

Clifford Avenue

Schedule Date: May 1 - May 10, 2018

Location Detail: Between Ada Drive and Cascade Road

​Mill and fill project. Road will be closed to through traffic during construction.

Clyde Park Avenue (Utility)

Schedule Date: May 29 – July 14, 2018

Location Detail: Alles Drive to 750 feet south

The utility project consists of sanitary sewer and water main extensions, private street entrance, road widening and resurfacing.

Crystal Springs Blvd., Crystal View Dr., and Hartman Dr.(COMPLETE)

Schedule Date: August 16 - August 22, 2018

Mill and repave will be completed with lane closures

Cutter Parkway, Eastmont, Kirk and Glen Meadow (S of Cascade Rd)

Schedule Date: May 7 - June 15, 2018

Location Detail: South of Cascade Road

Mill and fill projects. Construction will be completed with road closed to through traffic.

Page 1 of 2 pages  1 2 > 

x

Sign up for KCRC News