Burlingame Avenue |
0.1 Mile South of 84th Street |
Road Work
|
07/28/22 |
08/01/22 |
|
Closed to All Traffic
|
|
Division Avenue |
West River Drive to Bud Drive |
Mill & Fill
|
07/27/22 |
08/02/22 |
KCRC |
Lane Closures
|
Road work will be conducted under road work. |
68th Street |
Byron Center Avenue |
Utility Work
|
07/19/22 |
08/03/22 |
|
Lane Closures
|
|
White Creek Ave |
17 Mile Rd to Cedar Rv Dr |
Utility Work
|
06/14/22 |
06/24/22 |
|
Lane Closures
|
Southbound White Creek south of 17 Mile Rd for approximately 700 feet will have the right lane closed for utility work |
Fruit Ridge Avenue |
16 Mile Rd to 18 Mile Rd |
Crush & Shape
|
06/14/22 |
07/07/22 |
KCRC |
Detour for Through Traffic
|
This pavement replacement project is a crush, shape and repave with curp placement at various locations. |
Closed to through traffic
Jewell Avenue |
11 Mile Road to 10 Mile Road |
Utility Work
|
06/13/22 |
08/05/22 |
Utility |
Detour
|
Jewell Ave between 10 Mile Rd and 11 Mile Rd and 11 Mile Rd between Jewell and Algoma will be closed for water extension |
Closed to through traffic; open to properties within construction zone
Burlingame Avenue |
North of 84th Street |
Utility Work
|
06/13/22 |
06/17/22 |
|
Detour for Through Traffic
|
Open-cut excavation for two (2) sanitary sewer lateral connections in Burlingame Avenue and a separate full road width open-cut for 8 inch water main extension and tap. |
Closed
Jewell Avenue and 11 Mile Road |
|
Utility Work
|
06/13/22 |
07/29/22 |
Utility |
Detour for Through Traffic
|
Plainfield Water Supply System Extension – Area 8B. Approximately 6,800 feet of 12” water main installation along the west side of Jewell Avenue and north side of 11 Mile Road. |
Closed to through traffic; open to properties within construction zone
Spencer Township |
|
Resurfacing
|
TBD |
TBD |
KCRC |
Expect Delays
|
The Kent County Road Commission (KCRC) in collaboration with Spencer Township and Montcalm County Road Commission to complete a repaving of select local roads.
Current List of Roads
Projects in progress:
- 22 Mile Road: Amble Road to Trufant Avenue
- 22 Mile Road: Black Road to Sorensen Avenue
- 22 Mile Road: Mill Hill: Trufant Ave. to Black Road
- 22 Mile Road: Gravel Ridge to East County Line
|
Lincoln Lake Avenue |
Over Clear Lake |
Bridge Rehabiliation
|
06/06/22 |
07/01/22 |
|
|
|
Lincoln Lake Avenue |
18 Mile Road to Bradshaw Street |
Crush & Shape
|
06/06/22 |
07/01/22 |
KCRC |
Detour for Through Traffic
|
This project includes a crush and shape of the existing asphalt surface and placement of two (2) courses of HMA. Through traffic will be detoured. |
19 Mile Road |
Bass Lake to Montcalm Avenue |
Crush & Shape
|
06/06/22 |
06/30/22 |
KCRC |
Detour for Through Traffic
|
This project includes a crush and shape of the existing asphalt surface and placement of two (2) courses of HMA. Through traffic will be detoured. |
Closed to through traffic; open to properties within construction zone
Morse Lake Avenue |
60th Street to 68th Street |
Crush & Shape
|
05/31/22 |
06/20/22 |
KCRC |
Detour for Through Traffic
|
This pavement replacement project consists of a crush & shape with new curb and gutter at 60th Street. |
Morse Lake Avenue Detour
Plaza Center Drive |
68th St to Marketplace Dr Pvt |
Crush & Shape
|
05/25/22 |
06/10/22 |
KCRC |
Detour for Through Traffic
|
Crush & Shape is a structural pavement treatment that grinds, or crushes, the existing asphalt and 1-2” of underlying gravel. The material is then regraded, compacted and covered with multiple layers of paver-placed hot asphalt. |
Closed to through traffic; open to properties within construction zone
Belmont Avenue |
Post Drive to Pine Hill Drive |
Crush & Shape
|
05/23/22 |
06/06/22 |
KCRC |
Detour for Through Traffic
|
This project includes a crush and shape of the existing asphalt surface and placement of two (2) courses of HMA. Through traffic will be detoured. |
Closed to through traffic; open to properties within construction zone
Summit Avenue |
12 Mile Rd to 13 Mile Rd |
Crush & Shape
|
05/18/22 |
06/03/22 |
KCRC |
Detour for Through Traffic
|
Crush & shape full depth from 12 Mile Road northerly 1600 ft. Resurface remaining to 13 Mile Road. |
Detour for through traffic: Open for local traffic (properties within construction limits)
Herrington Avenue |
3,000 feet south of 10 Mile Rd to 10 Mile Rd |
Utility Work
|
05/17/22 |
07/01/22 |
Utility |
Detour
|
The project includes approximately 3,000 ft. of 16” water main installation along the west side of Herrington Avenue. Work also includes a 30” steel casing under 10 Mile Road installed by bore and jack methods. |
13 Mile Road |
Northland Drive and Tefft Avenue |
Crush & Shape
|
05/16/22 |
06/14/22 |
KCRC |
Detour for Through Traffic
|
The Kent County Road Commission (KCRC) in collaboration with Courtland Township is contracting with Superior Asphalt completed a full-width repaving of 13 Mile Road, Northland Drive to Tefft Avenue.
|
Detour for through traffic: Open for local traffic (properties within construction limits)
Knapp Street |
E of Dean Lake Ave to W of 1-96 |
Utility Work
|
05/16/22 |
06/09/22 |
Permit-Holder |
Detour for Through Traffic
|
This permitted work (non-KCRC) includes sanitary sewer extension, storm sewer work, and road widening to three-lane for new residential development on the north side of Knapp Street. |
Ramsdell Drive |
Krueter Rd to Belding Rd |
Utility Work
|
05/10/22 |
05/24/22 |
Utility |
Lane Closures
|
Right lane closures for utility work. |
Burton Street |
East of Kraft Ave to 1000 feet west of Cascade Road |
Mill & Fill
|
05/09/22 |
05/20/22 |
KCRC |
Detour for Through Traffic
|
This project includes a full-depth cold mill of existing two (2) lane and four (4) lane asphalt surfaces and placement of two courses of HMA. This project also includes concrete ramp improvements for an existing bike path. A detour is posted for traffic whose final destination is outside the closure limits.Through traffic will be detoured. |
Closed to through traffic; open to properties within construction zone
6 Mile Road |
M-37 (Alpine Ave) to Rusche Dr |
Utility Work
|
05/09/22 |
07/01/22 |
Utility |
Detour for Through Traffic
|
Sanitary sewer replacement. |
10 Mile Road |
west of Algoma Ave and east of Jewell Ave |
Utility Work
|
05/09/22 |
07/31/22 |
Utility |
Lane Closures
|
Lane closures for watemain work. |
Grand Rapids Township |
Neighborhood Streets |
Resurfacing
|
TBD |
TBD |
KCRC |
Expect Delays
|
KCRC in collaboration with Grand Rapids Township is contracting with Michigan Paving & Materials completed a full-width repaving of the following select local streets:
- Arbor Chase Drive: Atwater Hills Drive to 3 Mile Road
- Atwater Hills Drive: Mason Ridge Dr. to Arbor Chase Drive
- Mason Ridge Drive: Dunnigan Avenue to Atwater Hills Drive
- Amon Avenue: Elmer Drive to Valentine Street
- Boyes Avenue: Elmer Drive to Maryland Avenue
- Elmer Drive: Dean Lake Avenue to Maryland Avenue
- Maryland Avenue: Elmer Drive to Valentine Street
- Valentine Court: Dean Lake Avenue to End
- Valentine Street: Dean Lake Avenue maryland avenue
- Wilfred Avenue: Elmer Drive to Valentine Street
- Duchess Avenue: Reeds Lake to Reeds Lake Boulevard
- Kate Avenue: Reeds Lake to Reeds Lake Boulevard
- Lake Court: Reeds Lake to Duchess Avenue
- McCoy Drive: Reeds Lake to Duchess Avenue
- Reeds Lake: Reeds Lake Boulevard to Reeds Lake Boulevard
|
Alpine Township |
Neighborhood Streets |
Resurfacing
|
05/01/22 |
06/14/22 |
KCRC |
|
The Kent County Road Commission (KCRC) in collaboration with Alpine Township is contracting with Michigan Paving & Materials to complete a full-width repaving of select local streets during the 2022 construction season, including:
Completed 6/14/22:
- Hattus Avenue: Clark Street to Lamoreaux Drive
Completed 6/4/22:
- Baumhoff Avenue: 7 Mile Road to 8 Mile Road
- Peach Ridge Avenue: 4 Mile Road to 6 Mile Road
- 8 Mile Road: Peach Ridge Avenue to Walker Avenue
- 8 Mile Road: Walker Avenue to Bristol Avenue
|
68th Street |
at Plaza Center Drive |
Intersection Work
|
04/27/22 |
06/24/22 |
KCRC |
|
Modify and upgrade existing traffic signal, with box span configuration, LED signal heads, backplates and updated detection. |
Algoma Township |
Neighborhood Streets |
Resurfacing
|
TBD |
TBD |
KCRC |
Expect Delays
|
The Kent County Road Commission (KCRC) in collaboration with Algoma Township is contracting with Michigan Paving and Materials to complete a full-width repaving of select local streets. The project is to be completed within contract limits, May 1 and August 31, 2022, weather permitting.
Current List of Roads
Completed 6/16/22:
- Reburn Drive: Hull Street south to End
Completed 6/20/22:
- Tebeau Drive: Broman North to End
Completed 6/1/22:
- Summit Avenue: 12 Mile Rd. to 13 mile Rd
- Summit Avenue: 14 Mile (M57) to Russell Street
- 15 Mile Road: Algoma Ave. to Hoskins Avenue
- Grange Avenue: 13 Mile Rd. to 14 Mile Rd.
Information for Residents |
Patterson Avenue |
68th St to approximately 2,000 feet north |
Permit Work
|
04/25/22 |
06/30/22 |
Permit-Holder |
Expect Delays
|
Road widening, milling, resurfacing Patterson Avenue for addition of center-turn lane and driveway entrance to new Amazon site. Sidewalk and storm sewer culvert work also included. |
Division Avenue (Sparta Bridge #50) |
.2 Miles North of 11 Mile Road |
Bridge Improvement
|
04/18/22 |
05/18/22 |
KCRC |
Closed to All Traffic
|
Work will be conducted under a total road closure at the bridge. |
Detour for all traffic; complete road closure at bridge