Kraft Avenue

Schedule Date: April 15 - June 14, 2018

Location Detail: 36th St. to 28th St.

The project will consist of replacing the concrete bridge approach south of the highway overpass and cold milling and paving Kraft Avenue from north of 36th Street to Coach Drive. The project will be phased to maintain one lane of traffic in each direction at all times during construction.

Information

Phase 1 will consist of replacing the concrete bridge approach south of the highway overpass.  Construction will be done half-width by reducing traffic to one lane in each direction and shifting 2-way traffic to one side.

Phase 2 will consist of Cold Milling and Resurfacing Kraft Avenue from north of 36th Street to Coach Drive.  Construction will be done by reducing traffic to one lane in each direction and shifting 2-way traffic to one side.

Contractor: Rieth-Riley