Pine Island Drive at Post Drive (Completed)

Schedule Date: June 13 - July 25, 2018

Location Detail: Intersection Project

Widen and reconstruct to provide a left-turn on Pine Island Drive for southbound traffic to Post Drive. Work includes concrete curb and gutter, asphalt pavement, pavement markings, traffic signal upgrade and restoration.This project will be done in phases so that two-way traffic can be maintained at all times. 

Information

Traffic will be maintained throughout project with lane closures.

Phase 1 Pine Island Drive will be widened on the west side through HMA base course.

Phase 2 widening of Pine Island Drive will be done on the east side through HMA base course.

Phase 3 will consist of cold milling the center portion, paving base course and then paving entire project limits with hot mix asphalt (HMA) top course

 

Contractor: Michigan Paving & Materials