Cannonsburg Road at Myers Lake Avenue

Intersection Widening and Driveway Realignment

August 21 - September 30, 2017

Intersection Realignment to line up Cannonsburg Ski Resort Commercial Driveway with Myers Lake Avenue. Project will include trenching, underdrain installation, roadway widening, cold milling and HMA paving. A left-hand turn lane will be installed for EB and WB Cannonsburg Road at the new intersection. EB Cannonsburg Road will also feature a throughlane and dedicated right-turn lane at the ski resort.

Phase of Construction:

Initial work will focus on the Cannonsburg Ski Area driveway to accommodate MDOT’s use of Myers Lake Avenue as a detour route for the M-44 project. This initial work requires no lane closures and impact to traffic should be limited.

Beginning the week of September 11, a 15-day closure of Myers Lake Avenue from Cannonsburg Road to just south of Kreuter Road will be necessary. Message boards will be posted to provide advance notice of this closure and a detour route will be established along Ramsdell Drive.

Traffic Control:

For Cannonsburg Road, one lane of through traffic will be maintained at all times. Traffic on Myers Lake Avenue will be maintained, with the exception of a 15-day closure beginning the week of September 11– message boards will be posted to provide advance notice of this closure and a detour route will be established along Ramsdell Drive.


Colored areas on the map indicate Kent County cities and villages NOT within KCRC jurisdiction.

Contractor: Brenner Excavating
KCRC Engineer: Mike TenBrock