Thornapple River Drive

Schedule Date: July 9 - July 19

Location Detail: Cascade Road to Fase St.

Resurfacing project to include partial depth mill and fill  with 1.5 inch HMA (hot mix asphalt) overlay.

Information

The Kent County Road Commission has contracted Michigan Paving and Materials to resurface Thornapple River Drive. Beginning July 9, a portion of the road will be milled under a flagging operation. On July 15, paving is scheduled to begin and a single-course asphalt overlay will be applied. The road will be closed to through traffic during paving with a detour posted.

Flagging Operation: July 9 - July 12

Road Closed to through traffic; detour posted: July 15 - July 19