* Long-Range Strategic Investment Plan
2009
PRIMARY CONSTRUCTION
60th
Street – East and West of Kalamazoo Avenue
Reconstruct and widen to provide a
boulevard section with indirect left-turn lanes. Includes
concrete curb and gutter, storm sewer, sidewalk ramps, HMA pavement, full-depth
concrete pavement and traffic signal modifications. Two-way traffic (one-lane in each direction)
will be maintained during construction.
Contractor: Diversco
Construction
Start Date: April 9, 2009
Planned Completion Date: July 31, 2009
Northland
Drive – 13 Mile Road to 14 Mile Road (M-57)
Reconstruct and widen to five-lane
section. Includes concrete curb and gutter, storm sewer, and
HMA pavement. This project
includes replacement of the bridge over Stegman
Creek. Through traffic will be detoured.
Contractor: Milbocker &
Sons
Start Date: March 30, 2009
Planned Completion Date: August 28, 2009
Patterson Avenue – 28th Street to
Burton Street
Remove existing HMA pavement, install
42-inch diameter sanitary trunk sewer (City of Grand Rapids) and resurface
road. Includes
concrete pavement over HMA base (whitetopping). Through traffic will be detoured.
Contractor: Peters Construction
Start Date: April 1, 2009
Planned Completion Date: August 1, 2009
INTERSECTION PROJECTS
13
Mile Road @ Pine Island Drive
Reconstruct and regrade
13 Mile Road east and west of Pine Island Drive to improve intersection sight
distance. Includes earthwork, drainage, and HMA pavement. Through traffic will be detoured.
Contractor: Dykema Excavators
Start Date: April 13, 2009
Project Complete and Open to
Traffic: May 21, 2009
76th
Street and Riley Street @ Kenowa Avenue
Reconstruct and realign Riley Street
and 76th Street at the Kenowa Avenue
intersection. Includes
earthwork, culvert and drainage work and HMA pavement. Through traffic will be detoured.
Contractor: Diversco
Construction
Start Date: April 13, 2009
Estimated Completion Date: June 26, 2009
Lincoln
Lake Avenue @ 17 Mile Road
Reconstruct and regrade
Lincoln Lake Avenue north and south of 17 Mile Road to improve sight
distance. Includes
earthwork, drainage and HMA pavement.
Through traffic will be detoured.
Contractor: Dean’s Excavating
Start Date: June 15, 2009
Planned Completion Date: August 28, 2009
4
Mile Road & Fruit Ridge Avenue
Modify and upgrade existing traffic
signal. Maintain 2-way traffic with
intermittent lane closures.
Contractor: Strain Electric
Start Date: June 8, 2009
Planned Completion Date: August 28, 2009
Segwun Avenue & Grand River Drive
Extend left-turn lanes and install
traffic signal.
Crahen Avenue @ Bradford Street
Reconstruct and regrade Crahen Avenue north and south of Bradford Street to improve intersection sight distance. Includes earthwork, drainage and HMA pavement. Through traffic will be detoured.
BRIDGE PROJECTS
Algoma Bridge #25 – Northland Drive
over Stegman Creek
Remove
existing two span concrete bridge and construct single
span, 5-lane precast concrete I-beam bridge.
Contractor: Milbocker &
Sons
Start Date: March 30, 2009
Planned Completion Date: August 28, 2009
Remove existing single span steel
I–beam and concrete (jack arch) bridge and install a single precast concrete
box culvert.
Contractor: Kamminga & Roodvoets
Start Date: July 6, 2009
Planned Completion Date: August 28, 2009
NON-MOTORIZED PROJECTS
M-6 Trail (Phase 3) – Clyde Park
Avenue to Division Avenue
Construct a 10-foot wide HMA Trail
along the south side of M-6 between US-131 and Division Avenue. Construct a 10-foot wide trail along Clay
Avenue. Includes
bridges carrying the trail over Norfolk Southern Railway, Buck Creek and
Division Avenue.
Construct a 10-foot wide HMA trail
connecting with the existing Muskatawa Trail at 8th
Avenue in Ottawa County and the White Pine Trail in Comstock Park.