Major Primary Road Projects

Category Navigation

KCRC’s 2018 major primary improvement project information is available here.

2018 Primary Construction - Proposed

2018 Primary Construction - Proposed List

This list

  • is subject to change
  • does NOT include projects that will be identified based on surface evaluation conducted after the 2018 spring thaw and those added due to $3.3 million increase passed in March
  • does NOT include local road projects, which are scheduled and funded in collaboration with the townships

Five Year Improvement Plan

The KCRC Five Year Primary Road Improvement Plan:

  • Is subject to change
  • does NOT include local road projects, which are scheduled and funded in collaboration with the townships

HIGHWAY (MDOT) Projects

Construction on state and interstate highways and trunklines is within the jurisdiction of the Michigan Department of Transportation (MDOT), not the Kent County Road Commission.

Further information regarding work on state and interstate (US, M,I) can be found at:

MDOT 2018 Road Repair Projects

Mi Drive Interactive Map

KCRC’s Daily Work Schedule

TODAY’S SCHEDULE

Information regarding lane and road closures that correspond to work conducted by KCRC and our contractors. This list is updated Monday through Friday.

10 Mile Road

Schedule Date: May 7 - October 15, 2018

Location Detail: Alpine Avenue to Pine Island Drive

Reconstruct to 2-lane all season road standard. Work includes tree removal, earthwork, valley gutter, ditches, storm sewer, culvert replacement, HMA Pavement, pavement markings and restoration.This project will include widening and curb improvements at Vinton, Division, and Krupp avenues.

10 Mile Road (at Belmont Avenue)

Schedule Date: May 9 - May 18, 2018

Location Detail: just east and west of Belmont Avenue

The existing traffic signal at 10 Mile Road and Belmont Avenue will be removed and a concrete median divider will be constructed on 10 Mile Road to deter left-hand turns onto Belmont Avenue. Those seeking to make a left-hand turn from 10 Mile Road should now use the newly completed Belmont Bypass.

100th Street Bridge (MDOT - Emergency Repair)

Schedule Date: April 23 - May 23, 2018

Location Detail: Over US-131

100th Street Bridge is under the jurisdiction of the Michigan Department of Transportation (MDOT), not KCRC.

The Michigan Department of Transportation (MDOT) will begin emergency construction on the 100th Street Bridge over US-131 in Byron Township tomorrow, Monday, April 23 at 7PM - the bridge will remain closed to traffic through June 1.

The detour routes include:

EB 100th Street Detour: SB US-131 to 142nd Street to NB US-131 to EB 100thStreet

WB 100th Street Detour: NB US-131 to 84th Street to SB US-131 to WB 100th Street

The bridge was damaged when two semi-trucks with over-height shipping containers struck the overpass - this emergency repair project will restore two-way traffic.

MDOT has tentatively scheduled to replace and upgrade the bridge in 2020.

13 Mile Road (Proposed)

Schedule Date: TBD 2018

Location Detail: Kenowa Avenue to Peach Ridge Avenue

Reconstruct to 2-lane all season road standard. Work includes tree removal, earthwork, valley gutter, ditches, drainage, culvert extensions, HMA pavement, pavement markings and restoration.

14 Mile Road

Schedule Date: April 30 - May 11, 2018

Location Detail: Lymburner Avenue to Pine Island Drive

Project: ​Crush & shape, repave

16 Mile Road (Proposed)

Schedule Date: TBA 2018 (Proposed)

Location Detail: Keller Avenue to Harvard Avenue

The proposed improvement of 1.01 miles of 16 Mile Road from Keller Avenue to Harvard Avenue in Section 6 of Oakfield Township and Section 31 of Spencer Township includes necessary tree removal, grading, drainage, subbase, aggregate base and construction to provide for a 30-foot width roadway with HMA surfacing.

18 Mile Road

Schedule Date: TBD 2018

Location Detail: Wabasis Avenue to Meddler Avenue

Three inches will be milled and then a full Crush & Shape completed.

48th Street

Schedule Date: April 12 - May 25, 2018

Location Detail: East of Thornapple River Drive

The north side of the road approaching Thornapple River Drive is being widened to provide westbound to northbound right-turn lane. Road is being completed with shoulder closures.

60th Street (Utility Work)

Schedule Date: April 9 - July 16, 2018

Location Detail: Burlingame Avenue and Clyde Park Avenue

Work includes extending sanitary sewer and watermain within 60th Street right-of-way from 100 feet east of Burlingame Avenue to 700 feet east of Burlingame Avenue. Disturbed portion of 60th Street will be reconstructed to all-season.

68th Street at Madison Avenue (Proposed)

Location Detail: Traffic Signal Project

Modify and upgrade existing traffic signal, with box span configuration, LED signal heads, backplates and updated detection.

68th Street Bridge over the Thornapple River

Schedule Date: June 12 – July 26, 2018

The project includes bridge deck latex concrete resurfacing, hydro demolition, bridge joint replacement and approach work.
Traffic: bridge closure; detour posted

72nd Street

Schedule Date: TBD 2018

Location Detail: Byron Center to Burlingame; Ivanrest to Byron center

Two Phases:​

Byron Center to Burlingame (Mill & Fill)

  • Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be me

Ivanrest to Byron Center (Crush & Shape)

  • Crush & Shape is a structural pavement treatment that grinds, or crushes, the existing asphalt and 1-2” of underlying gravel. The material is then regraded, compacted and covered with multiple layers of paver-placed hot asphalt.

76th Street (Proposed)

Schedule Date: TBD 2018

Location Detail: West of US-131 to 300 ft east of Clyde Park Ave

Project: ​Mill & Fill and Resurfacing

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

82nd Street

Schedule Date: TBD 2018

Location Detail: Kenowa Avenue and Wilson Avenue

Project: Crush & Shape

Crush & Shape is a structural pavement treatment that grinds, or crushes, the existing asphalt and 1-2” of underlying gravel. The material is then regraded, compacted and covered with multiple layers of paver-placed hot asphalt.

Algoma Bridge #52 (Proposed)

Schedule Date: TBD

Location Detail: 10 Mile Road over the Rogue River

Preventative maintenance project including expansion joint replacement and box beam repair.

Alpenhorn Drive

Schedule Date: July 2 - August 31, 2018

Location Detail: .2 miles south of Lamoreaux Drive

Replacement of CMP culvert with a precast concrete box culvert. Bridge will be closed to all traffic - including pedastrian traffic - for the duration of the project.

Alta Dale Avenue

Schedule Date: August 7 - August 12, 2017

Location Detail: M-21 to Grand River Drive

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

Argo Street

Schedule Date: May 1 - May 10, 2018

Location Detail: Between Ada Drive and Cascade Road

Mill and fill project. Construction will be completed with road closed to through traffic.

Barn Ridge Drive

Schedule Date: TBD 2018

Location Detail: 9 Mile Road to End

Project: Mill and Fill

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

Bell Lake Drive

Schedule Date: May 17 - May 22, 2018

Location Detail: McCabe to the End

The paving project will include one course of 2” hot mix asphalt overlay.

Bella Vista Drive

Schedule Date: June 4 - June 15, 2018

Location Detail: Bella Vista (Belding Rd to Myers Lake)

Bella Vista: Mill & Fill (Resurfacing)
Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.
 

Belmont Avenue

Schedule Date: May 23 - June 8, 2018

Location Detail: Pine Hill Drive to South of Belmont Bypass

​Project: Crush & Shape and Resurfacing

Crush & Shape is a structural pavement treatment that grinds, or crushes, the existing asphalt and 1-2” of underlying gravel. The material is then regraded, compacted and covered with multiple layers of paver-placed hot asphalt. ("Road Closed" sign posted at 10 Mile Ave and Belmont Ave)

Belmont Avenue

Schedule Date: May 9 - May 23, 2018

Location Detail: Belmont Bypass to 10 Mile Road

​The project consists of a mill and fill. The road will be closed to through traffic for the project’s duration.

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

Belmont Bypass

Schedule Date: Completed May 4, 2018

Location Detail: South of 10 Mile Road

A new road is being constructed from 10 Mile Road and Thrifty Drive, south and west, to Belmont Avenue. Belmont Avenue is being widened from Graphic Drive south approximately 500 feet.Construction of new all season road will divert 10 Mile & Belmont Avenue left turns to the signalized intersection at the Meijer Entrance on 10 Mile Road. This project will provide for a three-lane roadway, with one lane in each direction and a center turn lane.

Bostwick Lake View Drive, Summerwind Avenue and Summer Lane Avenue

Schedule Date: June 6-June 11 2018

Location Detail: Bostwick Lake View Dr (9 Mile Road to End); Summerlane Avenue (5 Mile to Summerwind); Summerwind Avenue (5 Mile to end)

Project will include an Ultra Thin Overlay with a chipseal interlayer. 

Bristol Avenue

Schedule Date: May 2 - May 18, 2018

Location Detail: 4 Mile Road to Alpine Church Road

Project: Crosstile replacement and Crush & shape

Brower Lake Dr, Brower Ave and Oakview Ave

Schedule Date: May 22 - June 8, 2018

Project: Mill & Fill

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

Burrwood Street

Schedule Date: TBD 2018

Location Detail: Patterson Avenue to End

Mill and fill project. Construction will be completed with road closed to through traffic.

Caledonia Bridge #9 (Proposed)

Location Detail: 68th Street over the Thornapple River

Preventative maintenance project including concrete deck repair and overlay, deck joint replacement and concrete approaches.

Cannon Meadows Drive

Schedule Date: TBD 2018

Location Detail: Pettis to End

Project: Mill & Fill

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

Cannon Twp: Arroyo Vista Dr, Bella Vista, Knollcrest, Silverwick and Cannon Meadows

Schedule Date: May 16 - June 1, 2018

Location Detail: Arroyo Vista (Blakely to 9 Mile) Bella Vista (Belding Rd to Myers Lake) Knollcrest (Myers Lake to End) Silverwick (young to end) Cannon Meadows (Pettis to End)

​These streets will receive a full mill & fill.

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer - and in some cases the entire asphalt pavement thickness - with a milling machine and the replacement of the milled location with new asphalt. This process is used when a surface has deteriorated to poor condition and surrounding grades (i.e. curbs, driveways) must be met.

Cascade Bridge #27

Schedule Date: TBD - 2018

Location Detail: Thornapple River Drive just north of 60th Street

Culvert rehabilitation project to repair a portion of the existing twin corrugated metal pipe arches.

Cascade Road

Schedule Date: Week of May 29 – June 22, 2018

Location Detail: Fulton Street to East Beltline Avenue

Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer with a milling machine and the replacement of the milled location with new asphalt

Clifford Avenue

Schedule Date: May 1 - May 10, 2018

Location Detail: Between Ada Drive and Cascade Road

​Mill and fill project. Road will be closed to through traffic during construction.

Clyde Park Avenue (Utility)

Schedule Date: May 29 – July 14, 2018

Location Detail: Alles Drive to 750 feet south

The utility project consists of sanitary sewer and water main extensions, private street entrance, road widening and resurfacing.

Costa Avenue (utility work)

Schedule Date: April 23 - July 20, 2018

Location Detail: Providence Street to the north end

Utility project includes sanitary sewer and watermain work (Non-KCRC project)

Page 1 of 3 pages  1 2 3 > 

x

Sign up for KCRC News