Road: 13 Mile Road (Phase 2)

Limits: Pine Island Avenue to Edgerton Avenue

Work: Crush & Shape


Start: 05/24/21

Completion: 06/18/21


Traffic: Detour for Through Traffic

Contractor: Michigan Paving and Materials

This is a multi-phase resurfacing project to be completed in 2 phases: Phase 1 will include east of Alpine Avenue to Pine Island Drive; and Phase 2 will include the segment east of Pine Island Drive to Edgerton Avenue. Through traffic will be detoured. 

The project schedule is below and is subject to change:

  • Phase one: May 10 - June 4 (currently open to traffic)
  • Phase two: May 24 - July 2