Road: 68th Street
Limits: Eastern Avenue to Kalamazoo Avenue
Work: Mill and Fill
Start: 08/08/22
Completion: 09/30/22
Traffic: Lane Closures
Authority: KCRC
Contractor: Michigan Paving & Materials
This project includes the cold milling of the existing 4-lane asphalt surface and placement of two (2) courses of HMA. Upgrade sidewalk ramps to meet current ADA requirements.
Phase construction:
Phase 1 – sidewalk ramps, concrete curb & gutter, and manhole cover removal work
Phase 2 – Full closure (1 week) – mill & fill and HMA base
Detour via Eastern Avenue from 60th Street and Kalamazoo Avenue
Phase 3 – Raise manholes and place HMA top course
Through traffic will be maintained in Phases 1 and 3