Road: 84th Street
Limits: Division Avenue to Eastern Avenue
Work: Reconstruction
Start: 03/02/21
Completion: 07/07/21
Traffic: Detour
Authority: KCRC
Contractor: Kamminga and Roodvoets
Funding: $1,446,000 (KCRC - $214,000; Federal/State Aid: $1,232,000)
Improvement of 1.0 mile of 84th Street includes sanitary sewer installation, grading, drainage, subbase, aggregate base and construction to provide a three-lane roadway with curb and gutter, storm sewer, sanitary sewer, ditches and HMA surfacing.
Beginning March 2, DTE Energy will begin relocating portions of existing natural gas main at various locations that conflict with the planned road widening work. Sanitary sewer installation will follow by the Byron-Gaines Sewer Authority, and road improvement will be completed in the final phase