Road: 84th Street
Limits: Breton Ave to Hanna Lake Ave
Work: Reconstruction
Start: 07/21/21
Completion: 10/06/21
Traffic: Detour for Through Traffic
Authority: KCRC
Contractor: Brenner Excavating
Funding: $1,575,000
Reconstruct to 2-lane, all-season standard. Work includes stump removal, earthwork, ditches, culvert replacement or extension, HMA pavement, pavement markings and restoration. Through traffic will be detoured.