Road Limits Work Start Completion Authority Traffic
Road Limits Work Start Completion Authority Traffic
Honey Creek Avenue Knapp Street to 4 Mile Road Crush & Shape 06/05/23 06/23/23 KCRC Detour for Through Traffic

Crush and shape the existing asphalt surface and place two courses of HMA pavement. Project will be scheduled spring/summer 2023. 

  • Honey Creek Avenue from 4 Mile Road to 5 Mile Road will receive chip seal and fog seal preventive maintenance surface treatments during the 2023 construction season.
Reeds Lake Boulevard (EGR) Hall Street to Manhattan Mill & Fill 06/05/23 06/23/23 KCRC Detour for Through Traffic

This project is being completed in partnership with the City of East Grand Rapids.

  • Cold mill existing two-lane asphalt surface and place 1-2 courses of HMA pavement.
18 Mile Rd. (Tyrone Bridge 21) Over the Rogue River Bridge Rehabiliation 05/30/23 09/07/23 KCRC Detour

This bridge rehabilitation includes superstructure and partial substructure removal, guardrail and approach work.

Eastern Avenue 68th Street to 76th Street Mill & Fill 05/23/23 06/16/23 KCRC Two-way traffic maintained

The project will include milling, or removing, the existing roadway surface and placing two (2) courses of new asphalt pavement. Pavement markings will then be applied. Two-way traffic will be maintained using traffic shifts. Motorists should anticipate delay.

Packer Drive (Plainfield Bridge No. 12) Packer Drive Over the Rogue River Bridge Rehabiliation 05/22/23 07/22/23 KCRC Closed to All Traffic

Project will consist of: Box Beam Removal, Bridge Rail Removal, Cold Milling, Box Beam Replacement, Post-Tensioning, HMA Paving and Guardrail upgrade.

 

                                           

84th Street Hanna Lake Avenue to East Paris Avenue Reconstruction 04/10/23 06/21/23 KCRC Detour for Through Traffic

Reconstruct to 2-lane all-season standard. Work includes tree removal, earthwork, ditches, culvert replacement, HMA pavement, pavement markings and restoration.

Wiersma St. Algoma Ave to Simmons Ave Reconstruction 04/03/23 09/29/23 KCRC Detour

Reconstruction of unpaved road to paved road.

Cascade Road 36th Street to Whitneyville Avenue Reconstruction 04/03/23 06/30/23 KCRC Detour for Through Traffic

Road reconstruction and widening to add dedicated left-turn lane. Cascade Road will be CLOSED to through traffic with a posted detour using 36th Street to Buttrick Avenue. Work includes earthwork, concrete curb and gutter, storm sewer, drainage, HMA pavement, pavement markings and restoration.

This project will also include construction of a township-funded, non-motorized path on the easterly side of Cascade Road between 36th Street and Kenrob Drive.

10 Mile Road Pine Island Drive to Algoma Avenue Reconstruction 04/03/23 10/28/23 KCRC Detour for Through Traffic

Reconstruct to 2-lane all-season standard. Work includes tree removal, earthwork, ditches, culvert replacement, water main (Plainfield Twp), HMA (hot mix asphalt) pavement, pavement markings and restoration. (Tree removal began March 27).10 Mile Road is scheduled to be open to traffic by August 7 with final restoration completed by October 28, 2023.

Pine Island Drive House Street and 10 Mile Road Utility Work 03/27/23 07/03/23 Utility Lane shift

16-inch water main installation along the west side of Pine Island Drive from House Street to 10 Mile Road. Work will be completed under two-way lane shifts.

Conrail Avenue Homerich Avenue and Union Station Avenue Utility Work 01/09/23 07/21/23 Utility Detour for Through Traffic

The project will consist of HMA removal and placement of sanitary sewer, storm sewer, watermain, and reconstructing Conrail Avenue from Homerich Avenue to Union Station Avenue. Through traffic will be detoured to Byron Depot Drive via temporary access to Homerich Avenue, which is 300’ north of Conrail Avenue. The temporary access to Homerich Avenue off Byron Depot Drive will be removed once Conrail Avenue is reopened to traffic.