Project Details

< Back

Information

Road: Byron Neighborhoods (Phase II)

Limits: Byron Township

Work: Resurfacing


Start: 08/18/21

Completion: 10/20/21


Traffic: Expect Delays

Authority: KCRC

Contractor: Superior Asphalt

Funding: 50% KCRC/50% Byron Township

KCRC in collaboration with Byron Township is contracting with Superior Asphalt to complete a full-width repaving of select local streets.

  • 77th Street: Division Avenue to End (completed August 16)
  • Edgeview Avenue: 68th Street to Pine Bluff Court (postponed to coincide with future water/sewer project)
  • Pine Bluff Court: End to End(postponed to coincide with future water/sewer project)
  • Larry Street: 76th Street to Division Avenue (Completed August 16)
  • Alles Drive: Clyde Park Avenue to 440' West of Byron Commerce Drive

  • Alles Drive: Byron Commerce Dr to 440' West of Byron Commerce Drive