Clyde Park Avenue (NB) |
92nd Street to 100th Street |
Utility Work
|
09/19/23 |
09/30/22 |
Utility |
Lane Closures
|
Right lane closure for utility work |
Spaulding Avenue (Railroad) |
at Railroad Crossing |
Railroad Work
|
08/28/23 |
09/06/23 |
Permit-Holder |
Detour
|
Project consists of railroad crossing replacement. |
Closed to all traffic at railroad crossing
68th Street |
East of Clay Avenue at Railroad Crossing |
Railroad Work
|
08/21/23 |
08/27/23 |
Permit-Holder |
Detour
|
Reconstruction of the RR crossing |
Closed to all traffic at railroad crossing
Lamoreaux Drive |
East of Stony Creek |
Permit Work
|
08/16/23 |
08/21/23 |
Permit-Holder |
Lane Closures
|
Right lane closed for driveway work. |
Byron Depot Drive |
east of Homrich Avenue |
Utility Work
|
08/16/23 |
09/04/23 |
|
Detour
|
Replacing sanitary sewer, which ties to the manhole in the middle of Byron Depot. Detour: Use temporary road. |
Knapp Street |
west of I-96 |
Permit Work
|
08/14/23 |
08/18/23 |
|
Lane Closures
|
Right lane closed for driveway work. |
92nd Street |
east of Clyde Park Avenue |
Utility Work
|
08/14/23 |
08/23/23 |
Permit-Holder |
Lane Closures
|
Right lane closed gas main installation. |
Ada Drive |
Forest Hills Avenue and Spaulding Avenue |
Mill and Fill
|
08/10/23 |
08/18/23 |
KCRC |
Detour for Through Traffic
|
Ada Drive from Forest Hills Avenue to Spaulding Avenue will be milled full depth then repave. Spaulding Avenue / Ada Drive intersection and Spaulding Avenue 375 ft. north to Connemara Court will be milled partial depth (2”) and repaved. |
Closed to through traffic; open to properties within construction zone
E. Paris Ave |
From the Kentwood City limits to the 1100 block |
Utility Work
|
08/07/23 |
08/10/23 |
KCRC |
Lane Closures
|
Northbound E. Paris from the Kentwood City limits to the 1100 block the far right curb lane will be closed for utility work. Both daytime and nighttime closure |
12 Mile Rd |
Over US- 131 |
Bridge Improvement
|
08/07/23 |
08/14/23 |
KCRC |
Closed to All Traffic
|
12 Mile Rd over US-131 will be closed for bridge work |
Clyde Park Avenue |
at 60th Street |
Utility Work
|
08/07/23 |
08/15/23 |
Utility |
Closed to All Traffic
|
Installing sanitary sewer metering system in connection with City of Wyoming sewer. |
Egypt Valley Ave |
at 2 Mile Rd |
Utility Work
|
08/01/23 |
08/03/23 |
KCRC |
Lane Closures
|
Northbound Egypt Valley at 2 Mile will have a lane closure for gas main install. |
Northland Dr |
at Cedar Springs Ave intersection |
Intersection Work
|
07/26/23 |
08/11/23 |
KCRC |
Lane Closures
|
Northland Dr at Cedar Springs Ave intersection will have closures for intersection realignment and reconstruction. This project will be done in two stages: Phase 1 will consist of closing Northland Drive and the construction of Northland Drive north of Cedar Springs Avenue, and the relocated intersection of Cedar Springs Avenue. Phase 2 will consist of closing Cedar Springs Avenue between Northland Drive and Egner Street. This phase shall consist of the remaining relocation of Cedar Springs Avenue and the completion of Northland Drive between 18 Mile and Cedar Springs Ave |
Buttrick Ave |
Thornapple River Dr to Grand River Dr |
Resurfacing
|
07/24/23 |
08/03/23 |
KCRC |
Closed to All Traffic
|
Buttrick Ave from Thornapple River Dr to Grand River Dr will be closed for a mill and repave |
Coit Avenue |
Rifle Range Avenue to Hunsberger Avenue |
Crush & Shape
|
07/17/23 |
08/10/23 |
KCRC |
Detour for Through Traffic
|
COit Avenue from Rifle Range Road to Hunsberger Avenue will be crushed, shaped and repaved. This project will be completed using a detour, local traffic will be maintained. |
Detour for through traffic: Open for local traffic (properties within construction limits)
10 Mile Rd |
from Wolven Ave to Childsdale Ave |
Utility Work
|
07/17/23 |
07/24/23 |
KCRC |
Lane shift
|
10 Mile Rd from Wolven Ave to Childsdale Ave will have traffic shifts for watermain installation |
Thornapple Dr |
intersection with Tanglewood Dr |
Utility Work
|
07/17/23 |
07/28/23 |
KCRC |
Lane Closures
|
The intersection of Thornapple River Dr and Tanglewood Dr will have lane closures for watermain installation |
Parnell Avenue/Settlewood Drive |
M-21 (Fulton Street) to Foreman Street |
Crush & Shape
|
07/10/23 |
08/01/23 |
KCRC |
Detour for Through Traffic
|
Crush and shape the existing asphalt surface and place two courses of HMA pavement. |
Closed to through traffic; open to properties within construction zone
Northland Drive |
12 Mile Road to 14 Mile Road |
Mill and Fill
|
07/10/23 |
08/07/23 |
KCRC |
Lane Closures
|
Full Depth Cold mill existing 5-lane asphalt surface and three courses of HMA pavement. Milling and paving work will be phased to maintain two-way traffic at all times. |
Buttrick Avenue |
Grand River Drive to to 28th St |
Mill and Fill
|
07/07/23 |
07/21/23 |
KCRC |
Detour for Through Traffic
|
Full Depth Cold mill existing 2-lane asphalt surface and place 2 courses of HMA pavement. Project to be scheduled after July 9, 2023. |
Grand River Drive |
Buttrick Avenue to Snow Avenue |
Mill and Fill
|
06/21/23 |
07/07/23 |
KCRC |
Detour for Through Traffic
|
Mill & Fill is a structural pavement treatment that involves the removal of the existing surface layer with a milling machine and the replacement of the milled location with new asphalt. |
100th St. |
West of Byron Center Ave |
Utility Work
|
06/20/23 |
07/28/23 |
KCRC |
Lane Closures
|
Eastbound 100th St west of Byron Center Ave will have the right lane closed for utility work |
Ada Drive (7AM-7PM) |
Schoolhouse Drive and Bronson Street |
Permit Work
|
06/20/23 |
06/27/23 |
Permit-Holder |
Closed to All Traffic
|
Painting of murals at the train trestle site as part of the Downtown Development Authority's first public art initiative. |
Kraft Ave |
from Johnson St to 100th St |
Road Work
|
06/19/23 |
08/10/23 |
Permit-Holder |
Detour
|
Kraft Ave from Johnson St to 100th St will be closed for road construction.
Calpax expansion: open-cut water main and storm sewer crossing Kraft Ave at Duncan Lake Middle School Entrance. Kraft Ave widening, all season road construction, commercial drive entrance. |
Homerich Ave |
from 84th St to 92nd St. |
Crush & Shape
|
06/19/23 |
07/14/23 |
KCRC |
Detour for Through Traffic
|
Homerich from 84th St to 92nd St will be closed for a crush, shape and repave. |
Division Avenue |
6 Mile Road to 7 Mile Road |
Mill and Fill
|
06/19/23 |
07/09/23 |
KCRC |
Detour for Through Traffic
|
Cold mill existing two-lane asphalt surface and place two courses of HMA pavement. Targeted for Spring/summer 2023 start. |
Thornapple River Drive (7AM-7PM) |
Kamp Twins Drive to Fase Street |
Permit Work
|
06/17/23 |
06/20/23 |
Permit-Holder |
Closed to All Traffic
|
Information from Ada Downtown Development Authority:
Notice of upcoming road closures along Thornapple River Dr SE and Ada Dr SE. Thornapple River Dr SE will be closed to through-traffic at the vehicular train trestle from Saturday, June 17 through Monday, June 19.
Ada Dr SE will be closed to through traffic at the vehicular train trestle from Tuesday, June 20 through Tuesday, June 27. These road closures will be in place to facilitate the painting of murals at the train trestle sites as part of the Downtown Development Authority’s first public art initiative.
We’re anticipating painting to take place between the hours of 7 am and 7 pm during the road closure timeline. There will be no overnight road closures. Thornapple River Dr SE and Ada Dr SE will open back up to through traffic when painting ends each day. Please refer to the road closure maps provided for additional details regarding the detours.
Further road closure details can be found on our website: https://bit.ly/adamurals.
We thank you for your cooperation, and we look forward to the successful completion of this project |
84th St and Kalamazoo Ave |
Intersection |
Roundabout
|
06/12/23 |
08/02/23 |
KCRC |
Closed to All Traffic
|
Construct single-lane roundabout with concrete curb and gutter, 8-foot concrete sidewalk, asphalt paving, drainage, street lighting and restoration. Work will be phased and through traffic will be detoured.
* preliminary work by Consumers Energy begins May 9 under lane shifts in preparation for the roundabout project. |
|
from 200' south of Sandy Bottom to address #12475 |
Utility Work
|
06/07/23 |
06/22/23 |
Utility |
Lane Closures
|
right lane closed for utility work |
Podunk Ave |
from 200' south of Sandy Bottom to address #12475 |
Utility Work
|
06/07/23 |
06/29/23 |
Utility |
Lane Closures
|
right lane closed for utility work |
Honey Creek Avenue |
Knapp Street to 4 Mile Road |
Crush & Shape
|
06/05/23 |
06/21/23 |
KCRC |
Detour for Through Traffic
|
Crush and shape the existing asphalt surface and place two courses of HMA pavement. Project will be scheduled spring/summer 2023.
- Honey Creek Avenue from 4 Mile Road to 5 Mile Road will receive chip seal and fog seal preventive maintenance surface treatments during the 2023 construction season.
|
Detour for through traffic: Open for local traffic (properties within construction limits)
Reeds Lake Boulevard (EGR) |
Hall Street to Manhattan |
Mill and Fill
|
06/05/23 |
06/16/23 |
KCRC |
Detour for Through Traffic
|
This project is being completed in partnership with the City of East Grand Rapids.
- Cold mill existing two-lane asphalt surface and place 1-2 courses of HMA pavement.
|
|
|
|
06/05/23 |
06/09/23 |
|
|
|
|
|
|
TBD |
TBD |
KCRC |
|
|
18 Mile Rd. (Tyrone Bridge 21) |
Over the Rogue River |
Bridge Rehabiliation
|
05/30/23 |
09/15/23 |
KCRC |
Detour
|
This bridge rehabilitation includes superstructure and partial substructure removal, guardrail and approach work. |
Detour for all traffic; complete road closure at bridge
13 Mile Road |
Shaner Avenue to Myers Lake Avenue |
Crush & Shape
|
05/24/23 |
06/09/23 |
KCRC |
Detour for Through Traffic
|
Crush and shape the existing asphalt surface and place two courses of HMA pavement. |
Detour for through traffic: Open for local traffic (properties within construction limits)
Eastern Avenue |
68th Street to 76th Street |
Mill and Fill
|
05/23/23 |
06/09/23 |
KCRC |
Two-way traffic maintained
|
The project will include milling, or removing, the existing roadway surface and placing two (2) courses of new asphalt pavement. Pavement markings will then be applied. Two-way traffic will be maintained using traffic shifts. Motorists should anticipate delay. |
Packer Drive (Plainfield Bridge No. 12) |
Packer Drive Over the Rogue River |
Bridge Rehabiliation
|
05/22/23 |
08/06/23 |
KCRC |
Closed to All Traffic
|
Project will consist of: Box Beam Removal, Bridge Rail Removal, Cold Milling, Box Beam Replacement, Post-Tensioning, HMA Paving and Guardrail upgrade.
|
Detour for traffic; complete road closure at bridge
84th Street |
Wingeier Avenue to Freeport Avenue |
Crush & Shape
|
05/15/23 |
05/26/23 |
KCRC |
Detour for Through Traffic
|
Crush and shape the existing asphalt surface and place 2 courses of HMA pavement. |
Buttrick Avenue |
28th Street to Grand River Drive |
Culvert Work
|
05/10/23 |
05/18/23 |
KCRC |
Detour
|
Remove existing crosstiles/culverts and replace with new crosstiles/culverts. Daytime closures, only (7AM - 4PM). Road will be closed at the culvert. |
Grand Rapids Township |
Neighborhood Streets |
Resurfacing
|
05/01/23 |
06/01/23 |
KCRC |
Expect Delays
|
The Kent County Road Commission (KCRC) in collaboration with Grand Rapids Township is contracting with Rieth-Riley to complete a full-width repaving of select local streets. The project is to be completed within contract limits, May 1 and August 31, 2023, weather permitting.
- Alta Vista Drive: Cascade Road to Robinson Road
- Brentwood Drive: Park Hills Drive to Morningside Drive
- Elmhurst Avenue: Cascade Road to Robinson Road
- Glenview Drive: Cascade Road to Robinson Road
- Hathaway Drive: Park Hills Drive to Morningside Drive
- Kingswood Drive: Cascade Road to Fulton Street
- Lakeview Drive: Cascade Road to Robinson Road
- Midland Drive: AltaVista Drive to Elmhurst Avenue
- Midland Drive: Lake View Drive to Morningside Drive
- Montvale Drive: Glenview Drive to Elmhurst Avenue
- Morningside Drive: Cascade Road to Fulton Street
- Oak Hollow Drive: Lake View Drive to end (E. of Morningside)
- Park Hills Drive: Cascade Road to Fulton Streeet
- Uplands Drive: Park Hills Drive to Morningside Drive
- Reeds Lake: Hall Street to Gravel
Download Letter to Residents |
Courtland Township |
Local/Neighborhood Streets |
Resurfacing
|
04/28/23 |
06/08/23 |
KCRC |
Expect Delays
|
The Kent County Road Commission (KCRC) in collaboration with Courtland Township is contracting with Michigan Paving and Materials to complete a full-width repaving of select local streets. The project is to be completed within contract limits, May 1 and September, 2023, weather permitting.
- 13 Mile Rd: Shaner Ave to Myers Lake Ave.
- 11 Mile Rd: Myers Lake Ave. to Young Ave.
- Berrigan Ave: 13 Mile Road to 14 Mile Road
- Pine Lake Ave: 15 Mile Road to 16 Mile Road
|
Algoma Township |
Neighborhood Streets |
Resurfacing
|
TBD |
TBD |
KCRC |
Expect Delays
|
The Kent County Road Commission (KCRC) in collaboration with Algoma Township is contracting with Michigan Paving and Materials to complete a full-width repaving of select local streets. The project is to be completed within contract limits, May 1 and September, 2023, weather permitting.
- Scenic Pines Ct: Scenic Pines Dr. to End
- Scenic Pines Dr: Summit Avenue to End
- Valley View Drive: 12 Mile Road to End
- Division Ave: 13 Mile to 14 mile
- Division Ave: 14 Mile to 15 mile
|
Byron Township |
Neighborhood Streets |
Resurfacing
|
TBD |
TBD |
KCRC |
Expect Delays
|
The Kent County Road Commission (KCRC) in collaboration with Byron Township is contracting with Rieth-Riley to complete a full-width repaving of select local streets. The project is to be completed within contract limits, May 1 and September 1, 2023, weather permitting.
- Railside Dr: 76th St to Byron Station
- Railside Ct: Railside Dr. to End
- Beech Tree Dr: Railside Dr. to Byron Station Dr
- Byron Station Dr: Beech tree Dr to Byron Center Ave.
- Byron Station Ct: Byron Station Dr. to End
- Marfield Dr: Byron Center Ave to Parlo St
- Parlo Street: Marfield Drive to LaJean Drive
- Lajean Drive: Marfield Drive to End
- Red Osier Ct: Red Osier Drive to End
- Red Osier Dr: 76th Street to End
- Rush Creek Dr: Ivanrest to End
- Rush Creek Court: Rush Creek to End
- Bruce Scott Ct: Kelly Lee Dr to End
- Byron Shores Ct: Byron Shores Dr to End
- Byron Shores Drive: 68th Street to Byron Center Avenue
- Cattail Drive: 72nd St. to Lilly Pad Drive
- Country Springs Drive: Byron Shores Drive to Lily Pad Drive
- Egret Drive: Windrift Drive to Osprey Drive
- Kelly Lee Drive: 72nd Street to Byron Shores Drive
- Lilly Pad Drive: Country Springs Avenue to Windrift Drive
- Osprey Drive: Winterwind Drive to 72nd Street
- Windrift Drive: Lilly Pad Drive to Winterwind Drive
- Winterwind Drive: Windrift Drive to Osprey Drive
- Dust Rose Street: Indigo Ridge Drive to End
- Indigo Ridge Court: Indigo Ridge Drive to End
- Indigo Ridge Drive: Southwood Avenue to 76th Street
- Southwood Avenue: 72nd Street to End
- Homerich Ave: 92nd to 84th Street
- Ivanrest Ave: 60th Street to 76th Street
- 76th Street: Kenowa Avenue to Wilson Avenue
Notice to Residents |
84th Street |
Hanna Lake Avenue to East Paris Avenue |
Reconstruction
|
04/10/23 |
07/14/23 |
KCRC |
Detour for Through Traffic
|
Reconstruct to 2-lane all-season standard. Work includes tree removal, earthwork, ditches, culvert replacement, HMA pavement, pavement markings and restoration. |
Detour for through traffic: Open for local traffic (properties within construction limits)
Cascade Road |
36th Street to Whitneyville Avenue |
Reconstruction
|
04/03/23 |
06/15/23 |
KCRC |
Detour for Through Traffic
|
Road reconstruction and widening to add dedicated left-turn lane. Cascade Road will be CLOSED to through traffic with a posted detour using 36th Street to Buttrick Avenue. Work includes earthwork, concrete curb and gutter, storm sewer, drainage, HMA pavement, pavement markings and restoration.
This project will also include construction of a township-funded, non-motorized path on the easterly side of Cascade Road between 36th Street and Kenrob Drive. |
Closed to through traffic; open to properties within work zone
10 Mile Road |
Pine Island Drive to Algoma Avenue |
Reconstruction
|
04/03/23 |
08/31/23 |
KCRC |
Detour for Through Traffic
|
Reconstruct to 2-lane all-season standard. Work includes tree removal, earthwork, ditches, culvert replacement, water main (Plainfield Twp), HMA (hot mix asphalt) pavement, pavement markings and restoration. (Tree removal began March 27).10 Mile Road is scheduled to be open to traffic by August 7 with final restoration completed by October 28, 2023. |
Closed to through traffic; open to properties within construction zone
Pine Island Drive |
House Street and 10 Mile Road |
Utility Work
|
03/27/23 |
07/07/23 |
Utility |
Lane shift
|
16-inch water main installation along the west side of Pine Island Drive from House Street to 10 Mile Road. Work will be completed under two-way lane shifts. |
100th Street |
East Paris Avenue to Patterson Avenue |
Tree Work
|
01/20/23 |
02/03/23 |
KCRC |
Expect Delays
|
This phase of construction along Cascade Road will consist of tree removal. Traffic Control provided by SavATree will include flagging operation and associated signage. |
84th Street |
Hanna Lake Avenue to East Paris Avenue |
Tree Work
|
01/09/23 |
01/20/23 |
KCRC |
Lane Closures
|
This particular phase of construction on 84th Street will consist of tree removal. Traffic Control provided by Integrity will include portable stop/go lights (mechanical flaggers).
The anticipated start date of the all-season reconstruction project on 84th Street is scheduled to begin 04/03/2023. |