Road: Eastern Avenue
Limits: 68th Street to 76th Street
Work: Mill and Fill
Start: 05/23/23
Completion: 06/09/23
Traffic: Two-way traffic maintained
Authority: KCRC
Contractor: Rieth-Riley Construction
The project will include milling, or removing, the existing roadway surface and placing two (2) courses of new asphalt pavement. Pavement markings will then be applied. Two-way traffic will be maintained using traffic shifts. Motorists should anticipate delay.