Project Details

< Back

Information

Road: Sparta Bridge 28

Limits: 13 Mile Road .3 miles west of Alpine Avenue

Work: Bridge Improvement


Start: 04/05/21

Completion: 05/05/21


Traffic: Closed to All Traffic

Authority: KCRC

Contractor: J. E. Kloote Contracting

Funding: $230,000 - KCRC

This bridge rehabilitation project includes spot concrete box beam replacement, deck waterproofing, concrete abutment repair and new HMA surface.  This project will be done in conjunction with the 13 Mile paving project slated to begin in early May.  After bridge work is completed, and the paving contractor (Michigan Paving & Materials) for the 13 Mile project has mobilized, base paving operations will take place at the bridge and adjacent areas.